Project Description:

Full renovation and clean up. Remove all debris and dispose of. Fully board and install loft ladder hatch combination
Supply and fit 50sqm of SF19+
Loft hatch was the first job as access was limited. Rubbish all removed and boards fixed to joists.
Foil fixed under rafters and sealed to the floor over wall plate with mastic and staples/ batons

Key Details:

Project Installed By: Insulation installed and removed
Project Began: 2026-03-12
Project Ended: 2026-03-17
Project Size: 50
Project Location: Birmingham