Jeff and Pam

Project Overview

Project Description:

Remove all fibreglass and vacuum the area prior to superfoil install.
Check with technical team to advise on product specifications
Install 64 sqm of SF19+
Seal at wall plate with mastic and staples
Seal all joints and intrusions
Perform thermal testing to ensure no leaks were present and take photo evidence throughout the project .
Job turned out really well with thermals showing no leaks and obvious heat retention gained

Key Details:

Project Installed By: Insulation installed and removed
Project Began: 2025-10-15
Project Ended: 2025-10-16
Project Size: 64
Project Location: Birmingham